​14.02.2017

Wellcem restores production in a 49-year old well for PDO in Oman

 

​Fahud West 24, which accounts for a quarter of the field’s production, was drilled and completed in 1967 in the Natih reservoir but established an A-annulus pressure failure in 2014.


 

The breakthrough to fix an integrity problem without major maintenance or remedial workover could lead to the cost-efficient procedure being implemented on numerous wells in PDO.
Wellcem ThermaSet® sealant technology  was successfully utilized to restore well integrity and production with 41% less cost than a conventional workover.
 
More information in an article taken from PDO monthly newsletter for staff and contractors Al Fahal

 
 
 